Logo
Pattern

Discover published sets by community

Explore tens of thousands of sets crafted by our community.

Engineering Economics

24

Flashcards

0/24

Still learning
StarStarStarStar

Future Worth Analysis

StarStarStarStar

Future Worth Analysis finds the value of a present cash flow at a future date, accounting for interest or growth over time. Example Calculation:

FW=P(1+r)n FW = P(1+r)^n
where FWFW is the future worth, PP is the present value, nn is the number of periods, and rr is the interest rate.

StarStarStarStar

Break-Even Analysis

StarStarStarStar

Break-Even Analysis determines the point at which revenue equals costs, resulting in no net loss or gain. Example Calculation:

Break-Even Point (Units)=Fixed CostsPrice per UnitVariable Cost per Unit \text{Break-Even Point (Units)} = \frac{\text{Fixed Costs}}{\text{Price per Unit} - \text{Variable Cost per Unit}}

StarStarStarStar

Sunk Cost

StarStarStarStar

A sunk cost is a cost that has already been incurred and cannot be recovered. Example: Costs spent on research that did not lead to a viable product.

StarStarStarStar

Internal Rate of Return (IRR)

StarStarStarStar

IRR is the discount rate that makes the net present value of all cash flows (both positive and negative) from a particular project equal to zero. Example Calculation:

0=t=0nCt(1+IRR)t 0 = \sum_{t=0}^{n} \frac{C_t}{(1+IRR)^t}
Solve for the IRR where CtC_t is the cash flow at time tt and nn is the number of periods.

StarStarStarStar

Depreciation (Straight-Line Method)

StarStarStarStar

Straight-Line Depreciation is a method where the asset's cost is reduced uniformly over its useful life. Example Calculation:

Annual Depreciation=Initial CostSalvage ValueUseful Life \text{Annual Depreciation} = \frac{\text{Initial Cost} - \text{Salvage Value}}{\text{Useful Life}}

StarStarStarStar

Opportunity Cost

StarStarStarStar

Opportunity Cost is the value of the next best alternative forgone as the result of making a decision. Example: The cost of studying for an extra hour could be the leisure time sacrificed.

StarStarStarStar

Present Worth Analysis

StarStarStarStar

Present Worth Analysis discounts future cash flows to the present to compare different projects. Example Calculation:

PW=t=0nCt(1+r)t PW = \sum_{t=0}^{n} \frac{C_t}{(1+r)^t}
where PWPW is the present worth, CtC_t the cash flow at time tt, nn is the number of periods, and rr is the discount rate.

StarStarStarStar

Annual Worth Analysis

StarStarStarStar

Annual Worth Analysis converts cash flows of different amounts occurring over different times into a uniform annual series of cash flows. Example Calculation:

AW=PWAF AW = \frac{PW}{AF}
where AWAW is the annual worth, PWPW is the present worth, and AFAF is the annualizing factor.

StarStarStarStar

Life Cycle Cost Analysis (LCCA)

StarStarStarStar

LCCA is the total cost of ownership over the life of an asset. Example Calculation:

LCCA=Cinitial+t=1nCt(1+r)t LCCA = C_{initial} + \sum_{t=1}^{n} \frac{C_t}{(1+r)^t}
where CinitialC_{initial} is the initial cost, CtC_t is the cost at year tt, nn is the life of the project, and rr is the discount rate.

StarStarStarStar

Economies of Scale

StarStarStarStar

Economies of Scale occur when a company's production costs decrease as it produces more units. Example: A company may receive a discount on bulk orders of raw materials.

StarStarStarStar

Risk Analysis

StarStarStarStar

Risk Analysis involves quantifying the probabilities and consequences of risks. Example: Calculating the potential overruns in cost or time for construction projects.

StarStarStarStar

Sensitivity Analysis

StarStarStarStar

Sensitivity Analysis is used to understand how different values of an independent variable affect a particular dependent variable. Example: Assessing how changes in interest rates affect the outcome of a project investment.

StarStarStarStar

Net Present Value (NPV)

StarStarStarStar

NPV is the value of a series of cash flows over time, brought to the present. Example Calculation:

NPV=t=0nCt(1+r)t NPV = \sum_{t=0}^{n} \frac{C_t}{(1+r)^t}
where CtC_t is the cash flow at time tt, nn is the total number of periods, and rr is the discount rate.

StarStarStarStar

Marginal Cost

StarStarStarStar

Marginal Cost is the change in total cost that arises when the quantity produced changes by one unit. Example Calculation:

Marginal Cost=ΔCΔQ \text{Marginal Cost} = \frac{\Delta C}{\Delta Q}
where ΔC\Delta C is the change in costs and ΔQ\Delta Q is the change in quantity.

StarStarStarStar

Discount Rate

StarStarStarStar

The discount rate is the rate used to convert future economic value into present value. Example Calculation:

PV=FV(1+r)n PV = \frac{FV}{(1+r)^n}
where PVPV is the present value, FVFV is the future value, nn is the number of years, and rr is the discount rate.

StarStarStarStar

Cost Performance Index (CPI)

StarStarStarStar

CPI measures the financial effectiveness of project activities by comparing the budgeted cost of work performed with the actual cost. Example Calculation:

CPI=EVAC CPI = \frac{EV}{AC}
where EVEV is the earned value and ACAC is the actual cost of work performed.

StarStarStarStar

Payback Period

StarStarStarStar

The Payback Period is the time it takes for the cash inflows to repay the initial investment. Example Calculation:

Payback Period=Initial InvestmentAnnual Cash Inflow \text{Payback Period} = \frac{\text{Initial Investment}}{\text{Annual Cash Inflow}}

StarStarStarStar

Escalation

StarStarStarStar

Escalation refers to the provision in cost estimate for inflation or cost increases over time. Example: A construction project may factor in a 4% annual escalation in material costs due to inflation.

StarStarStarStar

Benefit-Cost Ratio (BCR)

StarStarStarStar

BCR is a ratio that compares the benefits of a project to its costs. Example Calculation:

BCR=t=0nBt(1+r)tt=0nCt(1+r)t BCR = \frac{\sum_{t=0}^{n} \frac{B_t}{(1+r)^t}}{\sum_{t=0}^{n} \frac{C_t}{(1+r)^t}}
where BtB_t is the benefit at time tt, CtC_t are costs at time tt, nn is the total number of periods, and rr is the discount rate.

StarStarStarStar

Return on Investment (ROI)

StarStarStarStar

ROI is a measure of the profitability and efficiency of an investment. Example Calculation:

ROI=Net ProfitInvestment Cost×100% ROI = \frac{\text{Net Profit}}{\text{Investment Cost}} \times 100\%
where Net Profit is the gain from investment minus the cost of investment.

StarStarStarStar

Inflation and Deflation

StarStarStarStar

Inflation is the rate at which the general level of prices for goods and services is rising, and subsequently, purchasing power is falling. Deflation is the decrease of the general price level. Example: If annual inflation rate is 3%, a 100productwillcost100 product will cost 103 next year.

StarStarStarStar

Externalities

StarStarStarStar

Externalities are costs or benefits incurred by third parties outside the transaction without compensation. Example: Pollution from a plant can affect the health of nearby residents without the plant incurring costs ('negative externality').

StarStarStarStar

Schedule Performance Index (SPI)

StarStarStarStar

SPI is a measure of schedule efficiency which is used to predict the project duration. Example Calculation:

SPI=EVPV SPI = \frac{EV}{PV}
where EVEV is the Earned Value and PVPV is the Planned Value.

StarStarStarStar

Engineering Economic Decision Matrix

StarStarStarStar

This matrix is a tool used to compare multiple projects or design alternatives based on several criteria (e.g., NPV, IRR, payback period). Example: A matrix comparing different engineering solutions for their expected costs, benefits, and economic payback times.

Know
0
Still learning
Click to flip
Know
0
Logo

© Hypatia.Tech. 2024 All rights reserved.